How nuclear reactors are made

Nuclear reactors produced by AEM-Technologies, JSC have a long service life (60 years) and overhaul period (up to 8 years), and also meet the most stringent safety requirements. The manufacture of reactors requires close adherence to all process standards, the availability of unique machines and units, and strict control at each stage.

Production process

01
02
03
04
05
Metallurgical blanks
Head stamping
Welding, overlay welding and heat treatment
Machining
Tests

Metallurgical blanks for the reactor pressure vessel are supplied from  AEM-Special Steels Plant. Large-sized blanks undergo incoming inspection, vertical lathe machine working of surfaces and weld grooves. After control operations, the blanks enter on the further process steps: assembly and welding.



A pearlitic steel slab is preheated in a furnace at a temperature of 1000 °C and then it is placed under max 15000 ton-force press, which forms a head of the slab. The double-acting hydraulic sheet-metal stamping press is unique and Russia’s only equipment that can stamp heads of a slab up to 380 mm thick.


Assembly and joining of two semi-vessels and welding of the closing weld are one of the key stages of the reactor vessel manufacturing cycle. Welding and  overlay welding are carried out automatically using a special installation. Heat treatment of blanks is carried out in gas-flame chamber furnaces to obtain the highest performance characteristics of products.


Machining process involves the manufacture of threaded holes for studs of the reactor main joint, as well as general work on finish machining of surfaces, welds, nozzles, hole drilling in internals. Thread cutting is performed using a CNC milling and boring machine. Thread milling provides high speed and accuracy of work. The total fleet of machining production of the plants of AEM-Technologies JSC includes many dozens of pieces of equipment: screw-cutting lathes, vertical lathes, boring machines, milling machines, band saws, deep drilling machines, etc.

 



During the entire reactor manufacturing process, most of the time is devoted to quality control tests. Radiographic test units are used to detect defects in thick-walled items. Quality control of welded joints is ensured by the use of liquid penetrant test and ultrasonic test procedures. In a specially equipped underground stand - a caisson - hydraulic tests are carried out. A pressure is injected into the body, in ten minutes the pressure should not fall.

In total, hundreds operations are carried out after jointing of the reactor semi-vessels. Particular attention is paid to non-destructive testing methods.

1 / 5
Quality control methods

768

total number of transactions

110

control tests

4900

surveillance specimens
Shipment and delivery

The equipment is delivered to the factory berth by special vehicles. Self-propelled and tractor-driven modular multi-axle trawls are used, which are capable of withstanding a load of over 400 tons. Loading operations are carried out using two cranes with a lifting capacity of 650 tons each.

01

Large weight and large dimensions of the reactor vessel

02

Availability of infrastructure and specialized equipment for transportation

03

Drawing up the optimal land and water route

04

Multi-stage coordination of transportation at all stages

05

Security and escort of transported objects