VVER-TOI

The latest reactor, created on the basis of VVER-1200 technical solutions, with improved technical and economic indicators and additional safety measures.

5 reactors

shipped

3 reactors

planned to be shipped by 2031.

Advantages over VVER-1200:

Specifications

3 300 MW

Thermal power

1 255 MW

Electric power

28 800 MW

The amount of energy generated per day with an 18-month fuel cycle

70 MW*day/kg

Maximum fuel burnup

72 hours

Time to ensure independence of the plant operation in case of a beyond design basis accident

163

Number of fuel assemblies

Economic characteristics

60 years

Life cycle

93 %

Installed capacity utilization factor

37,9 %

Efficiency (COP)

18 months

Duration of work without refueling

8 years

Overhaul period