VVER-1200

The up-to-date model of a water-cooled power reactor is developed on the basis of VVER-1000. It is supplied to nuclear power plants in China, Bangladesh, Belarus and other countries. For the first time, VVER-1200 uses unique engineering solutions in the field of safety, which makes it possible to classify the reactor plant as a generation III+ plant.

10 reactors

shipped

12 reactors

planned to be shipped by 2031

Advantages over VVER-1000:

Specifications

3 200 MW

Thermal power

1 200 MW

Electric power

28 800 MW

The amount of energy generated per day with an 18-month fuel cycle

72 hours

Time to ensure autonomy of the plant operation in case of a beyond design basis accident

70 MW*day/kg

Maximum fuel burnup

163

Number of fuel assemblies

Economic characteristics

100 years

Life cycle

90 %

Installed capacity utilization factor

18 months

Duration of work without refueling

35.9 %

Efficiency (COP)

4 years

Overhaul period

Production process

01
02
03
04
05
Production of metallurgical blanks
Bottom stamping
Welding, overlay welding and heat treatment
Machining
Tests

Metallurgical blanks for the reactor vessel are supplied from the AEM-Special Steels metallurgical complex. Large-sized blanks undergo incoming inspection, machining of surfaces and weld grooves on lathes. After the control operations, the blanks enter the following technological stages: assembly and welding.


A flat blank made of pearlitic steel is heated in a furnace at 1000 °C and then placed under a press with a maximum force of 15 000 tf, which forms the bottom of the blank. The double-acting hydraulic sheet punching press is unique and the only equipment in Russia that can stamp bottoms from blanks up to 380 mm thick.

Assembly and joining of two half-vessels and making of the closing weld are one of the key stages of the reactor vessel manufacturing cycle. Welding and overlay welding are carried out automatically using special equipment. Heat treatment of blanks is carried out in gas-flame chamber furnaces to obtain the highest performance characteristics of products.

The machining process includes the manufacture of threaded holes for the studs of the reactor main joint, as well as general work on the finishing of surfaces, welds, nozzles, drilling holes in the internals

During the entire reactor manufacturing process, most of the time is devoted to control tests. Radiographic test equipment is used to detect defects in thick-walled products. The control of welded joints is ensured by means of liquid penetrant and ultrasonic test procedures. In a specially equipped underground stand - a caisson - hydraulic tests are carried out. A pressure of 25.7 MPa (262 atm) is injected into the vessel, in ten minutes the pressure should not fall below 24.5 MPa (250 atm).

In total, hundreds operations are carried out after docking of the reactor half-vessels. Particular attention is paid to nondestructive testing methods.

1 / 5

Supply references

Bangladesh
Rooppur Nuclear Power Plant Unit No. 1,2
VVER-1200
  • Unit #1 - Shipment 2020
  • Unit #2 - Shipment 2021 
Belarus
Belarusian NPP Units No 1, 2
VVER-1200
  • Launch of Unit #1 - 2021
  • Launch of Unit #2 - 2022
China
Xudapu Nuclear Power Plant Unit No 3
VVER-1200
  • Unit #3 - Delivery 2023
China
Tianwan Nuclear Power Plant Unit No 7
VVER-1200
  • Unit #7 - Delivery 2023
Russia
NPP Leningradskaya-2 Units No 1, 2
VVER-1200
  • Unit #1 - Launch 2018
  • Unit #2 - Launch 2020
Russia
Novovoronezh NPP Units No 6,7
VVER-1200
  • Start-up of Unit #6 - 2016
  • Start-up of unit #7 - 2019